BF#7 blowing out carried successfully
Central Chronicle News
Bhilai, Aug 23: Blast furnace 7 blowing out activity was started on 20:40 hrs of August 20, 2021 and has been successfully carried. During this blowing out , the raw material burden has been brought down below the tuyere level this is very critical activity and is quite an accomplishment as its very rare exercise. Salamander tapping was also opened successfully at 19:25 hrs on August 21, 2021. Blast furnace-7 has completed its campaign life 17.60 MT during this campaign. After this Blast furnace 7 will undergo CAT- 1 capital repair.